Inspection and Planning Project for an Offshore Wind Farm


The challenge for the Parc du Banc de Guérande (PBG) is to manage the interfaces between the various contracting parties, the French authorities and stakeholders such as dockers, fishermen, etc.

Planning has delivered on all its promises with the presidential inauguration and commissioning of the park at the end of 2022.

480 MW(20% of the consumption of the region)
80 wind turbines

eocen's added value


  • Project process optimisation
  • Excellent management of the different interfaces between subcontractors.
  • Improved automated report solutions.
  • Improved performance indicators for piloting the project’s progress: rapid alerts on deviations and risks of deviations and implementation of mitigation strategies or recovery scenarios.